Skip to content

Construction update Oct. 2023: Granite panels are going up

A view of the Museum Building rising to the sky on the site of the Obama Presidential Center. Cranes are in the sky as work continues on the garage rooftop. Construction equipment is scattered throughout.

October 16, 2023 

The days may be getting cooler, but things are heating up at the Obama Presidential Center! Crews onsite are preparing to install the first granite panels that will clad the Museum Building.  This will be the most visible change in the next few months, but the Museum and Forum Buildings are also experiencing a lot of changes. Steel framing of the Auditorium has begun and the footprint of the Hadiya Pendleton Winter Garden can be understood for the first time. 

Down at the Lower Level, framing of the office space is in full swing. As shoring is removed, the future public spaces at the lower and street level of the Museum Building are also becoming defined. The relationship between the different spaces and the volume of the spaces is becoming distinguishable. Natural light is also starting to peek through. Work also continues on the Museum structure, with the elevator and stair cores now rising up to Level 6 at just over 150 feet tall. The floor slab for the top Exhibit Gallery will be poured later this month. The construction trailers and "huddle tent" that have served as the projects operations base for the last two years is being decommissioned so that the south end of the site can be prepared for construction of the Programs & Athletic Center, which will start in early 2024.

A view of the Museum Building rising to the sky on the site of the Obama Presidential Center. Cranes are in the sky as work continues on the garage rooftop. Construction equipment is scattered throughout.
Five workers stand on the platform in the north end of the Hadiya Pendleton Winter Garden. The columns on the left will frame the walls of the auditorium. Construction equipment is scattered throughout the building.
3D rendering of the Obama Presidential Center Plaza

Follow Along

Sign up for our new Obama Presidential Center Explorer email series and come along for the journey as we build the Center. We’ll have exclusive updates and previews all the way through our Grand Opening in 2025.

Help build the Obama Presidential Center

Your donation makes it possible for us to build a world-class museum, library, and gathering spaces on Chicago’s South Side.

Donate to the Barack Obama Foundation. The Barack Obama Foundation is registered as a 501(c)(3) non-profit organization (EIN 46-4950751).

More construction updates

A gray stone installation climbs up the north and east faces of the Museum Building at the Obama Presidential Center. Blue tarp-wrapped escalator bases are seen through an opening that will eventually be clad in an art glass installation. A clear blue sky is in the background.
  • Building the Center
  • Chicago

Concrete construction across the site is complete. The Sky Room and Oval Office are taking shape.

Learn more
On a clear blue-sky day, President Obama stands in a hard hat and a brightly colored safety vest at the Obama Presidential construction site and signs a beam. A large group of construction workers with various skin tones also wearing safety clothing surround him.
  • Building the Center
  • Chicago

The Museum Building at the Obama Presidential Center has reached its final height of 225 feet.

Learn more
A low angle shot shows workers on an orange basket lift affixing a panel of “Tapestry” stone to the lower west face of the Museum Building. A cloudy sunny sky is in the background.
  • Building the Center
  • Chicago

Check out the latest construction update at the Obama Presidential Center.

Learn more
President Obama is smiling wearing sunglasses, a white hardhat with the Obama Foundation rising sun logo, gloves, and a bright orange safety vest over a long dress coat. He is holding a cup of coffee and standing next to a white woman wearing a neon yellow construction coat, hard hat, and goggles. They are walking in front of three other people with a range of light to deep skin tones wearing orange safety vests and white hard hats. They are all walking in an unfinished building with scaffolding in the background.
  • Building the Center
  • Chicago

See the latest photos and stay up-to-date on the building process.

Learn more
A view of the Museum Building rising to the sky on the site of the Obama Presidential Center. Cranes are in the sky as work continues on the garage rooftop. Construction equipment is scattered throughout.
  • Building the Center
  • Chicago

The days may be getting cooler, but things are heating up at the Obama Presidential Center!

Learn more
A construction worker in a white hard hat and orange safety vest looks at a structure as he stands on  the concrete floor of Museum Building Level 3
  • Building the Center
  • Chicago

Construction has reached the third floor, where a reconstruction of the Obama Oval Office will be on exhibit.

Learn more
On a clear day, a crane rises up behind a concrete building that’s under construction. In the foreground sits a rust-colored industrial trash bin and to the right, a construction worker wearing a white hard hat and yellow safety vest looks down at a pile of building material.
  • Building the Center
  • Chicago

It has been a season of great progress! The height of the stair and elevator wells have passed the halfway-point of the building.

Learn more
A massive crane stands high above a construction site.
  • Building the Center
  • Chicago

Work on the Museum building has reached an exciting milestone with the placement of the street level deck to form the concrete floor at this level.

Learn more
A construction site with scaffolding, concrete and rebar. Two people wear neon yellow and hard hats on the right side.
  • Building the Center
  • Chicago

Major structural work on the underground parking garage is complete!

Learn more
Two construction workers wearing bright orange and yellow vests  and white hard hats appear to unload planks of wood. They stand in a cavernous room of concrete filled with insulation and other building materials.
  • Building the Center
  • Chicago

As the Center continues to take shape, we are thrilled to reach a new milestone in its construction.

Learn more
A building being constructed of concrete at the Obama Presidential Center. Beams and rebar can be seen in scaffolding. A worker is wearing orange and working in the background. The sky is gray.
  • Building the Center
  • Chicago

Construction at The Center has picked up considerably since the holidays, aided by the unseasonably mild weather.

Learn more


 A wide shot of the construction on the site of the Obama Presidential Center in the daytime.
  • Building the Center
  • Chicago

As construction of the Obama Presidential Center enters its second year, the focus is almost entirely on concrete.

Learn more
missing
  • Building the Center
  • Chicago

The organization is on track to meet its ambitious workforce and business diversity goals for construction.

Learn more
A construction site showing scaffolding and rebar
  • Building the Center
  • Chicago

The majority of columns for the lower level of the parking garage have been cast and construction of the concrete walls is nearly complete.

Learn more
People wearing neon yellow safety gear gather around Barack Obama as he shakes hands with a woman in the center. A white tarp is behind them.
  • Building the Center
  • Barack Obama

Watch as President Obama surprises the construction crew and tours the site.

Learn more
A wide view of a construction site with metal pilings and rebar.
  • Building the Center
  • Chicago

Mass excavation and earth retention is complete and the focus is now squarely on concrete operations.

Learn more
A construction site with concrete and scaffolding. A building is at the center with a red scaffold in the middle.
  • Building the Center
  • Chicago

Two tower cranes were installed to facilitate the construction of the Garage and Museum Building.

Learn more
A construction site filled with mud and concrete. Large metal tubing is on either side and a wood staircase is in the back center of the frame.
  • Building the Center
  • Chicago

A metal perimeter around the subterranean level of the main buildings and parking garage will prevent water from infiltrating the buildings.

Learn more
A wide shot of snow-covered ground and buildings in the background. The sun is shining in a blue sky.
  • Building the Center
  • Chicago

Progress on constructing the Obama Presidential Center continues with relatively few inclement weather delays.

Learn more
A snowy, muddy construction site with the rectangular outline of metal and red pipe.
  • Building the Center
  • Chicago

Drilling for geothermal wells is nearly complete, and work to connect the wells through a series of lateral ducts is about a third of the way finished.

Learn more
Two men in neon yellow construction jackets and hardhats stand waist-deep in a dirt trench. Behind them are construction vehicles and a blue sky with buildings.
  • Building the Center
  • Chicago

Drilling began for the first caissons that will support the underground parking garage.

Learn more
People explore the sky room of the future Obama Presidential Center
  • Building the Center
  • Chicago

This event will bring members of the disabilities community up to speed on the current approach to inclusive design at the OPC.

Learn more
Barack and Michelle Obama with shovels in their hands, smiling at the camera, pretending to dig in a pile of dirt. A man stands on one side of them, Mayor of Chicago Lori Lightfoot holds a shovel on the other side.
  • Building the Center
  • Barack Obama

Mayor Lightfoot and Governor Pritzker joined President and Mrs. Obama for the ceremony, each sharing remarks.

Learn more
A slightly-angled graphic rendering of a large, white rectangular building surrounded by green fields, white pathways and trees. A road is on one side and a body of water on the other.
  • Building the Center
  • Chicago

Roadway improvements will continue and construction will begin within the 19.3 acre site of the Center that sits within Jackson Park.

Learn more
A mostly green and gray site-plan map of the Obama Presidential Center with a focus on buildings, pathways and roads.
  • Building the Center
  • Chicago

Expect lane closures as preparatory work to remove the existing median on Cornell Drive and install a new one begins.

Learn more